SERVICES

Avalon Condo’s, CT

FSI installed IBO rods and tiebacks to hold back a 10 concrete wall of varying heights. First walls were cored, then IBO rods were drilled and grouted. Plates, nuts, and washers were installed and all tiebacks were post-tensioned to 15 tons to meet design requirements and apply load to the wall.

  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
  • slider-image
Project Name and Location:
Avalon Condo's, CT
Project Date:
1997
Project Type:
Concrete wall stabilization
Piles Specification:
114 IBO rods and tiebacks
Soil & Embedment Depth:
15 - 25 feet
Project Timeline:
3 Weeks